Topic: Talking About The Characteristics Of Crane Installation And Its Import

The quality of Crane factory installation has a great impact on the installation engineering, the service life of the crane's structural parts and parts, the crane design efficiency, production use and safety, and economic benefits.

The lifting equipment installation project starts from the unpacking of the equipment to the completion of the equipment installation, and the commissioning, trial operation is qualified, and the project acceptance is completed. As the crane is a special equipment, it has the characteristics of high risk. Therefore, in the installation of the crane, safe work is particularly important, and special attention should be paid to the following aspects:

1. Cranes are mostly mechanical equipment with huge structures and complex mechanisms, which are usually difficult to transport as a whole. The equipment is often transported separately and assembled at the use site as a whole. Therefore, the overall qualification of the crane must be reflected through the correct installation, and the integrity and integrity of the whole crane can be inspected.

2. The crane runs on the user's site or the track of the building. Therefore, for its running track or installation foundation, as well as for the crane itself, whether it can cooperate with each other well, whether it is suitable for operation and whether it can meet the strict requirements of use, it must be concluded through correct installation and trial operation and inspection after installation. .

3. The crane has extremely high safety requirements, and the safety devices must be complete and installed correctly to achieve reliable, flexible and accurate technical requirements.

4. According to the importance of the safe work of the crane, in order to make the crane meet the requirements of various loads after it is put into use, the crane must be tested with no load, full load, and overload according to the regulations. These tests must be carried out in the operating state of the crane mechanism or in a specific static state. This requires the crane to be handed over to use after the load test is carried out after the crane is installed.

5. Flexible parts such as the steel wire rope of the crane and many other parts will experience some elongation, deformation, and loosening after the initial load. This also requires repair, correction, adjustment, treatment and tightening after the crane is installed and loaded and tested. Therefore, a series of work such as crane installation, trial operation, and adjustment must be done to ensure the safe and normal use of the crane in the future.

Talking About The Characteristics Of Crane Installation And Its Importance Guidance